Two numbers drive a PCT timeline: 18 and 30.
Iraq's PCT membership took effect on 30 April 2022, with a 30-month national-phase deadline. That date is the starting point for anyone thinking about the PCT route into Iraq.
The first mark is about 18 months. WIPO publishes a PCT international application shortly after 18 months from the priority date, unless it is withdrawn earlier.
The second mark is about 30 months. National phase entry under the PCT is usually required about 30 months from the earliest priority date. So the priority date is the anchor for both marks, and it is worth recording on the day it is set.
A simple PCT timeline
- 01
30 April 2022
Iraq's PCT membership took effect
- 02
Shortly after 18 months from priority
WIPO publishes the international application, unless withdrawn earlier
- 03
About 30 months from the earliest priority date
National phase entry is usually required